6 OPERATION
If the oil heater is de-energised during a
shutdown period, it must be energized for 24
hours prior to starting the compressor.
6.1 General
YS chillers are designed to work independently, or in
conjunction with other equipment via a York ISN
building management system or other automated
control system. The compressor can be started and
loaded as required using a range or input signals to
achieve the desired cooling effect. This section
describes the normal procedures for operation of the
unit and should be read in conjunction with the control
centre Operation Instruction.
6.2 Pre-Startup
Prior to starting the chiller, observe the control centre.
Make sure the display reads SYSTEM READY TO
START.
The internal clock, all the control setpoints and any other
required settings, eg., daily schedule, should be
programmed before the unit is started. (Refer to Control
Centre Operation Instruction).
If the chilled water pump is manually operated, start the
pump, the control centre will not allow the unit to start
unless chilled liquid flow is established through the unit.
If the chilled liquid pump is wired to the control centre the
pump will automatically start.
6.3 Start-up
1. To start the chiller, press the compressor START
switch. This switch will automatically spring return
to the RUN position. When the start switch is
energised, the control centre is placed in an
operating mode and any fault will be shown by a
display message.
Any faults which occur during STOP/RESET
are also displayed.
The slide valve is returned to the unload
position automatically when the unit is shut
down to prevent loading the compressor on
start-up.
When the unit starts, the following automatic sequences
are initiated: (Refer to Figure 6.1 Starting & Shutdown
Sequence).
1. The control centre display message will read
SYSTEM START SEQUENCE INITIATED for the
first 30 seconds of the starting sequence.
2. The measured oil and evaporator pressures are
compared during system equalization so that any
offset is stored for use in calculating deferential trip
points during compressor operation.
3. The chilled liquid pump contacts close starting the
chilled liquid pump to allow liquid flow through the
cooler. The chilled water flow switch is bypassed
for the first 25 second of the start sequence.
4. After 30 seconds of start sequence operation, the
compressor will start. While the motor is
accelerating to full speed the control centre display
will read: SYSTEM RUN - CURRENT LIMIT IN
EFFECT.
5. When the motor reaches full speed and the current
falls below 100% FLA the message will read:
SYSTEM RUN - LEAVING TEMP. CONTROL.
6. The anti-recycle timer begins after the 30 seconds
of pre-run time. The timer will run for 30 minutes
after the compressor starts. If the unit shuts down
during this period of time it cannot be started until
the timer completes the 30 minute cycle.
For display messages and information
pertaining to operation, refer to the control
centre Operating Instruction.
035L02381-GB0 6-1